Water Reclamation Plant Treatment Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Improvements to the Water Reclamation Plant (WRP) are needed to increase the efficiency and reliability of plant operations. This project will be completed in two phases.

Phase one consists of rehabilitation and process improvements to the primary and secondary treatment facilities including:

  • Rehabilitating
    • existing influent pumps,
    • primary clarifier structures and equipment,
    • primary effluent pump station structure and equipment, and
  • Replacing
    • electrical systems supporting the primary treatment area, and 
    • mechanical equipment inside Secondary Clarifier No. 2. 

Phase two of the project includes:

  • Primary sludge piping modifications,
  • Primary sludge pump room exhaust fan and drain replacements,
  • Ferric chloride facility rehabilitation including new tanks, piping, and supports,
  • Primary odor control tower replacement,
  • Secondary clarifier tanks 1& 3 piping, gate, and concrete improvements,
  • Secondary diversion box replacement,
  • Pumping facility concrete rehabilitation,
  • Mixed liquor distribution box concrete repair and gate replacements, and
  • Equalization basin pump and piping upgrades. 

Equipment additions and rehabilitations will increase the efficiency and reliability of plant operations. Structural rehabilitation will extend the useful life of the related structures. Ventilation and odor control improvements will reduce odors at the plant and reduce future corrosion. Improvements to the secondary clarifiers will improve the reliability of the system and extend its overall life. 

Clarifier and Killer Whale Mural at the Livermore Water Reclamation Plant

Checklist iconProject Schedule and Status
Payment iconEstimated Funding and Project Cost
Open book pages iconAdditional Resources